Page 1 of 1

Change work flow items

Posted: 17 Oct 2010, 12:13
by HomesicK
Hi guys,,

Could you please tell me how to customize the work flow items (new, feedback, acknowledged…) ,, to delete, modify or add some others items ??

Thanks

Re: Change work flow items

Posted: 17 Oct 2010, 18:09
by istvanb
Hi,

please read the following topic: http://www.mantisbt.org/forums/viewtopi ... 772#p32772

That topic is about a different problem, however you will find the answer to your question!

let me know if you need more help!
i-

Re: Change work flow items

Posted: 20 Oct 2010, 06:05
by HomesicK
Thanks my friend ,, it works :D
u r great man ;)