new status always added to all projects

Posted: 13 Feb 2018, 20:15
by titovetch
every time i create a new status to be used for one project ,its always reflected on the other projects and i need to remove it from the all projects manually.

on other hand its reflected on the workflow transitions and not visually useful because its extend the page otherwise statues appeared on the view issues => filterer

can we have the option to select which status included on the project

Re: new status always added to all projects

Posted: 17 Feb 2018, 15:56
by titovetch
is this an issue or not reported behavior , if yes ! how can i bypass that

Re: new status always added to all projects

Posted: 17 Feb 2018, 22:36
by atrol
I don't understand your issue
titovetch wrote: 13 Feb 2018, 20:15i create a new status to be used for one project
What exactly do you do?
titovetch wrote: 13 Feb 2018, 20:15its always reflected on the other projects
Same for this, what you mean with it?

Maybe some additional screen shots help to understand.

Re: new status always added to all projects

Posted: 18 Feb 2018, 12:01
by atrol
For the moment I set the issue you opened to resolved https://www.mantisbt.org/bugs/view.php?id=23938

Re: new status always added to all projects

Posted: 18 Feb 2018, 20:33
by titovetch
I have created 5 new issue status to be used in Project-B and i found that these new status have been added to Project-A & Project-C and all checkbox are marked (new status VS old status)in workflow transation so i must open each project to unmark these status because i want to use in Project-B only,i hope it clear now

Re: new status always added to all projects

Posted: 18 Feb 2018, 20:53
by atrol
titovetch wrote: 18 Feb 2018, 20:33 I have created 5 new issue status to be used in Project-B
Still the same. What does it mean? What did you do?

Re: new status always added to all projects

Posted: 19 Feb 2018, 17:08
by titovetch
add a custom status and Define in the enumeration (in the config file)

$g_status_enum_string =(Configured Status)

Re: new status always added to all projects

Posted: 19 Feb 2018, 18:19
by atrol
titovetch wrote: 19 Feb 2018, 17:08 (in the config file)
Config file means, that the configuration is used for ALL projects, but you want
titovetch wrote: 18 Feb 2018, 20:33to be used in Project-B
So you have to use page Manage > Manage Configuration > Configuration report to set a project specific option.
Set value of field configuration option to status_enum_string