Hello,
I am using Mantis 1.2.2 and for some reason the Roadmap is not accurately calculating the % of reports closed. It used to work. I double-checked and the versions have not been released except one but it will not show the others either. Any ideas?
Thanks in advance!
SD
Roadmap Not Calculating
Moderators: Developer, Contributor
Re: Roadmap Not Calculating
Is there one project, or more than one?
Is there any subproject?
How many issues have set the target version to the version you are talking about?
How many issues have status new, feedback, acknowledged, confirmed, assigned, resolved, closed?
What is displayed at the bottom of the roadmap? (Something like 21 of 63 issue(s) resolved. Progress (33%).)
Is there any subproject?
How many issues have set the target version to the version you are talking about?
How many issues have status new, feedback, acknowledged, confirmed, assigned, resolved, closed?
What is displayed at the bottom of the roadmap? (Something like 21 of 63 issue(s) resolved. Progress (33%).)
Re: Roadmap Not Calculating
Hello!
I was able to figure it out. I changed the status Resolved to another name and so it did not connect with the new status. I changed it back and it worked.
Thanks!
SD
I was able to figure it out. I changed the status Resolved to another name and so it did not connect with the new status. I changed it back and it worked.
Thanks!
SD