Description

Would be nice to have a feature like the one present in FlySpray about milestones: define milestones, and assign which bugs should be fixed to approach thay milestone.

For example:
Whe have bugs 1,2,3,4 and 5. For releasing 1.0 version, 1 and 2 should be fixed. Then developers know exactly what they have to do for specific version. In reports, should be a "1.0 milestone report: 1 of 2 bugs fixed (50%)". If 3, 4 and 5 are planned for 1.1 version, we could have another milestone for 1.1 and assign those bugs to it.

Additional Information

Sorry for mentioning FlySpray, it´s only for better describe what I´m asking. Mantis is my choice anyway :)

TagsNo tags attached.

Relationships

duplicate of 0004711 closedvboctor Create roadmap from feature requests in versions 

Activities

frentmeister

frentmeister

2006-08-25 03:24

reporter   ~0013329

Yes we need this Fature too.....

This a good Idea, because the View is realy good, and the planing of the Milestones then more better....

ryandesign

ryandesign

2006-08-28 16:46

reporter   ~0013338

There are several ways to accomplish that in Mantis.

  1. You can create a master ticket for each version of the project you plan to release, then make relationships between that ticket and all the other tickets that need to be resolved before that project version can be released. This is what I do, and also what the Mantis project itself does (e.g. 0005410). Make the master ticket depend on all those other bugs; then it's clear that they need to be resolved before the version can be released.

  2. You can create a new custom field with version numbers, and use that to track the version in which you expect to resolve an issue.

Bithunter

Bithunter

2006-08-29 07:09

reporter   ~0013341

Yes, you always can use a pipe wrench to nail a nail, but it´s better to use a hammer! :)
Please, visit the demo of FlySpray, and see http://forums.mantisbt.org/viewtopic.php?t=1903

frentmeister

frentmeister

2006-08-29 07:23

reporter   ~0013342

ryan, nice Feature, but we are not a little Firm, we Programming some big Game and then we have 10.000 Bugreports and more in Open Beta, better is a Programmed Feature because the Relationship into a Bug are not sortable, and by 10000 Issue you become a list like the Bible...;)

vosskaem

vosskaem

2006-10-04 08:56

reporter   ~0013580

I like to vote for this feature too.
Here is another example for an implementation
http://www.hosted-projects.com/trac/TracDemo/Demo/report/3
and a nice view for it
http://www.hosted-projects.com/trac/TracDemo/Demo/roadmap

sik0fewl

sik0fewl

2006-12-19 16:51

reporter   ~0013849

I would also like to see this feature. ryandesign's solution might work in the meantime, but it's somewhat of a hack. It's also nice to see the progress that is done so far.

Here's what Trac's looks like (vosskaem's links seem to be broken):

http://trac.edgewall.org/roadmap
http://trac.edgewall.org/report/6

vboctor

vboctor

2006-12-20 05:15

manager   ~0013852

This feature was already implemented in 1.1.0a2.